Cyprus is unlikely to begin importing LNG before the end of 2028, with Energy Minister Michael Damianos now expecting gas to be available by the end of 2029, as efforts to complete the long-delayed Vasilikos import terminal continue.

Mr Damianos said on 27 October that state-owned Etyfa is evaluating the technical and financial credentials of the eight firms that expressed interest in the remaining construction work ((MEES, 16 October)). Prequalification is due to finish by early January 2027, with a new contractor to be appointed before summer 2027. Construction should take around 18 months once work resumes. (CONTINUED - 137 WORDS)