No.
|
|
Project Description
|
Client
|
|
|
|
|
1
|
 |
Algeria
|
| 1.1 |
|
In Salah Gas - Southern Fields Development Project: CPF 500 MMSCFD/ 2 dehydration trains and dehydration tr. 360 mmscfd + P/L |
IN Salah Gas (JV of Sonatrach, BP & Statoil) |
| 1.2 |
|
Inlet Separation and Boosting Unit at Alrar: Gathering Lines, Manifolds, Separation/Compression, Tie-in with existing facilities |
Sonatrach |
| 1.3 |
|
Timimoun Natural Gas Project |
Total + Sonatrach + Cepsa |
|
Drilling around 40 wells to tap eight structures over an area of 2,500 sq. km. |
|
Construction of gas gathering and processing facilities. |
|
Pipeline. |
|
|
Total Approximate Value
|
$2088mn
|
|
|
|
|
2
|
 |
Azerbaijan
|
| 2.1 |
|
Baku International Sea Trade Port |
Ministry of Transport |
|
Reclamation 3 Mio m3 |
|
Jetty 1,200m |
| 2.2 |
|
Oil & Gas Processing and Petrochemical Complex: i45-50km South of Baku at Sangachal |
SOCAR |
|
40bn cu m gas processing plant, 300,000b/d refinery, chemical, petrochemical power plants |
|
|
Total Approximate Value
|
$1415mn
|
|
|
|
|
3
|
 |
Bahrain
|
| 3.1 |
|
BAPCO Refinery Expansion: Capacity from 250,000b/d to 350,000b/d |
BAPCO |
| 3.2 |
|
GCC Railway Network: The rail has a total length of 2177km, with Saudi Arabia (695km) and the UAE (684km) having the longest lines. Oman (306km), Bahrain (64km), and Kuwait (145km) |
GCC Technical Committee |
|
|
Total Approximate Value
|
$4550mn
|
|
|
|
|
4
|
 |
Iraq
|
| 4.1 |
|
Nassiriyah Oil Field Development: CPF and Pipelines |
Ministry of Oil |
|
Location: 400km North of Basra |
|
Modularization is considered due to security issues |
| 4.2 |
|
Tuba Field Expansion |
AOC 20%, Mitsui 30%, JOGC 50% |
|
South Iraq, near Kuwait Border. |
|
300,000bpd CPF and pipeline |
|
|
Total Approximate Value
|
$1875mn
|
|
|
|
|
5
|
 |
Jordan
|
| 5.1 |
|
Jordan National Red Sea Water Project |
MWI |
|
The JRSP implementation plan is divided into five consecutive and financially independent phases. At full development (Phases I - V) the project will include the following features: |
|
1. Delivers 860mcm of fresh water to Jordan which includes up to 240mcm of cooling water for the Jordan Atomic Energy Commission. |
|
2. Provides up to 300mcm of fresh water for other regional water supply customers and needs. |
|
3. Provides up to 1320mcm of water (desalination brine and seawater) to save and stabilize the Dead Sea. |
|
4. Provides up to 280 megawatts of "green" hydro-electric. |
| 5.2 |
|
Marsa Zayed Aqaba |
Al Maabar |
|
Development of land of the existing port. |
|
Phase (1): 33 storey mix use tower (146 houses, one marina, total 300,000m2 area. |
| 5.3 |
|
National Railroad Network |
Ministry of Transport |
|
3 Packages: |
|
508.6km Aqaba-Syrian Border |
|
78.5km Mafraq-Irbid |
|
381.3km Zarqa-Iraqi Border-Saudi Border |
| 5.4 |
|
Risha Gas Field: 350km east of Amman, currently producing 21 mcfpd to be increased to 250 mcfpd |
BP 49%, GOJ 51% |
|
|
Total Approximate Value
|
$20650mn
|
|
|
|
|
6
|
 |
Kazakhstan
|
| 6.1 |
|
Karabatan Integrated Gas Chemical Plant Ethane Cracker 833ktr: 800,000 tpy polyethylene, 400,000 tpy polypropylene |
Kazakhstan Petrochemical Industries (KPI); [KMG 51%, SAT 24.5%, L.BASEL 24.5%] |
| 6.2 |
|
Karachaganak III: Drill 65 new production and 18 new injection wells and to build 2 additional technological lines for oil stabilization in addition to 6 (+1 reserved) additional compressor of gas re-injection. Increase maximum gas production at the field to 38.5bn cubic meters per year and to reach nominal gas exports figure at 16bn cubic meters per year. |
KPO |
|
Expect 5 Packages: 1) Process, 2) Gas Injection, 3) Power, 4) Pipelines, 5) Early Works |
| 6.3 |
|
Kashagan Oil Field Development Phase II: Increase oil production from 450,000bpd to 900,000bpd |
KazMunayGas stake has increased to 16.81%, ENI (16.81%), ExxonMobil (16.81%), Shell (16.81%), Total (16.81%), ConocoPhillips (8.40%), INPEX (7.56%) |
| 6.4 |
|
Kashagan Oil Field Development Phase III: Onshore EPC: Increase oil production from 900,000bpd to 1,200,000bpd |
KazMunayGas stake has increased to 16.81%, ENI (16.81%), ExxonMobil (16.81%), Shell (16.81%), Total (16.81%), ConocoPhillips (8.40%), INPEX (7.56%) |
|
|
Total Approximate Value
|
$32200mn
|
|
|
|
|
7
|
 |
Kuwait
|
| 7.1 |
|
Az Zour Refinery - Offsites & Utilities: Main power distribution, steam generation unit, air systems unit, central cooling water and distribution unit, water systems facilities, site preparation, administration building complex and enterprise integration and communication systems. |
KNPC |
| 7.2 |
|
Az Zour Refinery - Process Package 1 |
KNPC |
|
615,000 bpd of Crude Oil |
|
3 x 205,000 bpd CDUs |
|
3 x 11,000 bpd ARDS units |
|
3 x 62,000 bpd Diesel Hydrotreaters |
|
3 x naphtha 180,000 bpd hydrotreaters |
|
3 x kerosene 53,000 bpd hydrotreaters |
|
2 x 1000 bpd sat gas plants LPG & 60MMSFD refinery |
|
Heavy Oil Cooling HP/LP flares |
| 7.3 |
|
Fourth Petroleum Liquid Gas at Mina Ahmadi Refinery |
KNPC |
| 7.4 |
|
GCC Railway Network: The rail has a total length of 2177km, with Saudi Arabia (695km) and the UAE (684km) having the longest lines. Oman (306km), Bahrain (64km), and Kuwait (145km) |
GCC Technical Committee |
| 7.5 |
|
Heavy Oil Facilities: Build, operate and maintain temporary heavy oil handling and processing facilities in North Kuwait |
KOC |
| 7.6 |
|
KNPC Clean Fuels Refinery: Major Upgrade/expansion of MAA and MAB refineries. |
KNPC |
| 7.7 |
|
Sheikh Jaber Al Ahmad Al Sabah Causeway Doha Link: Design and construction of 11km causeway from Shuwaikh port to Doha 6.7km as viaduct |
MPW |
| 7.8 |
|
Sheikh Jaber Al Ahmad Al Sabah Causeway Main Link: Design and construction of 35.6km causeway mainly as viaduct and includes one cable stayed bridge. |
MPW |
|
|
Total Approximate Value
|
$18700mn
|
|
|
|
|
8
|
 |
Libya
|
| 8.1 |
|
Petrochemical Complex: Expand Ras Lanuf Petrochemical Complex plus refurbishment of existing units (Naptha cracker and two polyethylene units) |
NOC/Dow Chemicals JV, 50/50 |
| 8.2 |
|
Ras Lanuf LNG Plant: Capacity depends on gas availability but the plan is that the plant will replace Marsa Al-Brega LNG. |
SHELL |
| 8.3 |
|
Waha Development: Increase current production capacity of 350,000 bpd to 400,000 bpd. Gas Plant, Pipeline & Facilities |
Waha Oil Co. (LNOC 59.17%, ConocoPhillips 16.33%, Marathon 16.33%, Amerada Hess 8.17%) |
|
|
Total Approximate Value
|
$8760mn
|
|
|
|
|
9
|
 |
Oman
|
| 9.1 |
|
Duqm Refinery & Petrochemical Complex |
Ministry of Oil & Gas + private |
|
300,000 bpd |
|
800,000 tpy sytrene |
|
2,800,000 tpy Aromatics |
|
1,500,000 tpy Polypropylene |
|
A 300,000 bpd refinery might be added |
| 9.2 |
|
EPC Isomerisation Plant B in Sohar |
|
| 9.3 |
|
GCC Railway Network: The rail has a total length of 2177km, with Saudi Arabia (695km) and the UAE (684km) having the longest lines. Oman (306km), Bahrain (64km), and Kuwait (145km) |
GCC Technical Committee |
| 9.4 |
|
Petrochemical Plant |
|
| 9.5 |
|
Salahah Port Expansion, Berths 7, 8, & 9 |
Salahah Port Services Co. (SAOG) |
| 9.6 |
|
Sohar Refinery Extension |
|
|
|
Total Approximate Value
|
$18105mn
|
|
|
|
|
10
|
 |
Qatar
|
| 10.1 |
|
Al Shaheen Refinery at Mesaieed: 200,000-250,000 bpd to produce distillates, bitumen and green coke. Package 3 - SRU, Tale Gas, AGU Utilities |
QP |
| 10.2 |
|
Barzan Gas Development - Onshore. 1700 mmscfd of gas. First Phase: Inlet facilities, condensate stabilisation uni, C2, C3, C4 & NGL recovery, dehydration unit, amine recovery, fractionation unit, sour water stripping, storage & loading facilities, offsites & utilities. The first phase is two LNG trains |
QP/Exxon Mobil, 90%/10% |
| 10.3 |
|
Gas Recovery: Also known as "Jetty boil-off Project" minimize loss of LNG. |
Qatargas |
| 10.4 |
|
QAFAC II Project: 6750 tpd methanol + 1000 tpd ammonia |
QAFAC (JV 50%, QP 20%, China Petroleum, 15% Lee Chang, 15% Octane Canada) |
| 10.5 |
|
Qatar Railway: Will cover Greater Doha as a start, then express cargo rail will link Industrial Area to the other parts of the country |
Qatari Diar |
| 10.6 |
|
Ras Laffan Condensate Refinery: Expansion from 146,000 bpd to 292,000 bdp |
Laffan Refinery Co. (QP 51%, Total 10%, ExxonMobil 10%, Cosmo Oil 10%, Idemitsu 10%, Mitsui 4.5%, Marubeni 4.5%) |
| 10.7 |
|
Ras Laffan Olefins Complex |
QP 51%, ExxonMobil 49% |
|
1.6m t/y ethane cracker with downstream units. |
|
650,000 tpy LLDPE |
|
650,000 tpy LDPE |
|
700,000 t/y Ethylene Glycol |
|
|
Total Approximate Value
|
$25690mn
|
|
|
|
|
11
|
 |
Saudi Arabia
|
| 11.1 |
|
GCC Railway Network: The rail has a total length of 2177km, with Saudi Arabia (695km) and the UAE (684km) having the longest lines. Oman (306km), Bahrain (64km), and Kuwait (145km) |
GCC Technical Committee |
| 11.2 |
|
Jizan Refinery Project |
Saudi Aramco |
|
250,000 - 40,000 b/d |
|
Phase I: Hydroskimming |
|
Phase II: Completion |
| 11.3 |
|
Jubail Petrochemical Complex (previously at Ras Tanura) |
Aramco + Dow Chemicals |
|
Offsites and Utilities incl. power water & storage facilities - $3000mn |
|
Polyethylene Plant |
|
1.2mty ethane/nptha steam cracker |
|
Aromatics complex |
|
Pipeline |
|
70,000b/d high olefins fluid catalytic cracker unit - $1000mn |
|
Polypropylene plant |
|
Polyethylene teraphthalate |
|
Polyethylene teraphthalate |
|
Pure teraphthalate acid fac. |
|
Toluene diosocyanate unit |
|
Chlorakali facility producing 640,000 t/y |
|
Acrylonitrile unit |
|
Styrene butadine rubber |
| 11.4 |
|
Jubail Petrochemical Complex: 1.2mtpy cracker and also includes four downstream process units producing 400,000 t/y of linear low-density polyethylene (HDPE), depending on the grades produced, acrylonitrile and propylene produced from propane dehydrogenation (PDH) plant. |
INEOS Enterprises + Delta Oil Co. |
| 11.5 |
|
King Abdallah Sports City |
Aramco/Laing O'Rourke |
|
Full sports city north of Jeddah (near Kaust) |
|
Stadium 100,000 Spectators |
|
Several sports arenas |
|
Support buildings including hospital and hotel |
| 11.6 |
|
Luberef Expansion Project at Yanbu: Increase UDU capacity from 26.1 to 40 mbd, PDA from 6.5-12.5 mbd and a new 23 mbd lube hydrocracker |
Luberef (Aramco 70% Jadwa Invest. 30%) |
| 11.7 |
|
Medina Airport: BTO for 25 years to Design and Build an 8 Million Passenger per year terminal (Phase 1) and Extension of Runway and associated Aprons/Taxiways |
GACA/TAV-Oger-Rajihi |
| 11.8a |
|
Petro-Rabigh Expansion Phase II - Expansion of Rabigh Aromatics Complex: 3 million tpa of Naptha |
Petro-Rabigh (JV Aramco + Sumitomo 50/50) |
| 11.8b |
|
Petro-Rabigh Expansion Phase II - Expansion of Rabigh Ethane Cracker: 30 mmscfd of Ethane |
Petro-Rabigh (JV Aramco + Sumitomo 50/50) |
| 11.9 |
|
Ras Al-Zour Aluminum: 4 mtpy aluminum refinery and a 1.8 mtpy aluminum smelter |
Maaden 60%, Alcoa 40% |
| 11.10 |
|
Samref - Yanbu Refinery Upgrade: Hydrogenation unit, Splitter, Naptha hydrotreater, Distillate hydrotreater (40,000bpd), Sulpher recovery unit, Sour water stripper, handling facilities and utilities & offsite facilities. |
Samref (Exxon Mobil 50%, Saudi Aramco 50%) |
| 11.11 |
|
Shaybah Gas Development, Offsites & Utilities NGL recovery facility |
Aramco |
| 11.12 |
|
Shaybah Gas Plant: Up to 7.2b cf/d, six NGL trains between 2014-2033 in four phases: 1st phase 2014-2017: two trains to produce 2.4b cf/d, 2nd phase 2018-2023: for 1.2b cf/d, 3rd phase 2024-2028: for 2.4b cf/d, 4th phase 2029-2033: sixth train for 1.2b cf/d |
Aramco |
| 11.13 |
|
Wasit Gas Development: 2.5B scufpd of gas from Arabiyah and Hasbah Fields. Four gas trains, four sulpher trains, fractionation unit, four cogen and utilities |
Aramco + Dow Chemicals |
| 11.14 |
|
Yanbu Polybutylene Terephthalate (PBT) Complex 60,000 tpa |
Oos Petrochemical Company |
| 11.15 |
|
Yanbu Polysilicon Plant: 5,000 tpy polysilicon |
IDEA International (consortium of Businessmen) |
|
|
Total Approximate Value
|
$76520mn
|
|
|
|
|
12
|
 |
Turkmenistan
|
| 12.1 |
|
South Yoloten Gas Field Development: Process, Offsites & Utilities, and Export Pipeline |
State Concern Turkmengas |
|
|
Total Approximate Value
|
$3600mn
|
|
|
|
|
13
|
 |
United Arab Emirates
|
| 13.1 |
|
ABBR Project: Asab Grassroot Central Degassing Station + Booster Station + Pipeline for Lean Gas. Also will involve Bu Hasa Sour Gas Injection, Bab Debottlenecking and Ruwais modification. |
Gasco |
| 13.2 |
|
Abu Dhabi International Airport Terminal: Increase the annual passenger-handling capacity at the airport from 12 million to 32 million |
ADAC (Abu Dhabi Airports Co.) |
| 13.3 |
|
Abu Dhabi Polymers Park: Plastic Conversion facilities such as packaging, pipes, and cables. Location: Abu Dhabi Industrial City |
ADBIC |
| 13.4 |
|
Aluminum rolling Mill at Taweelah: Capacity 500,000 tpy located at Khalifa Port, raw material from EMAL |
ADBIC |
| 13.5 |
|
Borouge IV |
Borouge (Adnoc 60%, Borealis 40%) |
| 13.6 |
|
Carbon Storage Site: Carbon Capture and Storage of 20mtpy |
MASDAR |
| 13.7 |
|
Chemaweyaat (Tacaamol) Petrochemical Complex at Taweelah: |
Chemaweyaat (IPIC 40%, ADIC 40% ADNOC 20%) |
|
Urea Fertilizer plant, aromatics and advanced polymers facilities |
|
135000 tonnes per annum (tpa) of Aromatics |
|
550000 tonnes per annum (tpa) of LLDPE |
|
750000 tonnes per annum (tpa) of Ethylene Oxide |
|
1450000 tonnes per annum (tpa) of Naphtha |
|
350000 tonnes per annum (tpa) of LDPE |
|
160000 tonnes per annum (tpa) of Bis-phenol |
|
900000 tonnes per annum (tpa) of Mono Ethylene Glycol |
|
340000 tonnes per annum (tpa) of Benzene |
|
200000 tonnes per annum (tpa) of Butadiene |
|
130000 tonnes per annum (tpa) of Polycarbonate |
|
100000 tonnes per annum (tpa) of Ethanol Amine |
|
400000 tonnes per annum (tpa) of Cumene |
|
3000 tonnes per annum (tpa) of Triethylene Glycol (TEG) |
|
140000 tonnes per annum (tpa) of Methyl Tertiary Butyl Ether (MTBE) |
|
950000 tonnes per annum (tpa) of Polyethylene |
|
1000000 tonnes per annum (tpa) of Urea |
|
420000 tonnes per annum (tpa) of Polypropylene |
|
1370000 tonnes per annum (tpa) of Paraxylene |
|
80000 tonnes per annum (tpa) of Melamine |
|
110000 tonnes per annum (tpa) of Acetone |
|
60000 tonnes per annum (tpa) of Phenol |
| 13.8 |
|
Inter Refinery Pipelines Phase II |
Takreer |
| 13.9 |
|
Louvre Abu Dhabi Museum |
TDIC |
| 13.10 |
|
Ruwais Hydrogen Power Plant: World's largest including desalination |
MASDAR 60%/Hydrogen Energy 40% (BP) JV |
|
420MW +20-25 mgpd |
|
Feedstock is 100 mcfpd natural gas |
|
Resulting carbon dioxide will be used for reinjection |
| 13.11 |
|
Steel Plant (Phase III): 1.2-1.3 mtpy flat products |
Abu Dhabi Emirates Steel (ESI) |
| 13.12 |
|
Union Railway (Part of GCC Railway Network): 1st Phase in Abu Dhabi is 264km in Ruwais-Shah Area. |
Union Railway |
|
|
Total Approximate Value
|
$40890mn
|
|
|
|
|
14
|
 |
Yemen
|
| 14.1 |
|
Aden Refinery |
Ministry of Oil |
|
150,000bbl/day (CDU) |
|
Heavy refining, ARDS unit and RFCC. |
|
Naptha and unleaded urea unit, NHT, CCR, PENEX, Sulfoline |
|
|
Total Approximate Value
|
$995mn
|
|
|
|
|
|
|
|
|
|
|
Aggregate Total Approximate Value
|
$220038mn
|
|
|